
2-10 t/h (series to 100 t/h)
DZL Chain Grate Biomass Steam Boiler
Packaged three-pass biomass steam boiler, 2-10 t/h at up to 1.6 MPa, with a light chain grate and water-cooled arches.
View details3 t/h biomass steam boiler at 1.0 MPa on rice husk, commissioned in 2023 in Trujillo, Peru: the mill generates husk only during the harvest and needs steam all year.

3 t/h at 1.0 MPa, fired on rice husk, was commissioned in 2023 for a agriculture plant in Trujillo. The mill generates husk only during the harvest and needs steam all year. The fix was a DZL series unit selected on the measured load, not on the nominal process rating.
The site had grown around a boiler that was never re-sized as the process changed. Nobody had measured the header, so the shortfall was blamed on the boiler’s age. The site runs one extended shift and the steam demand is set by batch equipment rather than by a continuous process, so the load curve has a sharp morning peak and a long plateau.
| Item | Value |
|---|---|
| Model | DZL series, 3 t/h |
| Working pressure | 1.0 MPa |
| Fuel | rice husk |
| Full-load fuel demand | 1 kg/h |
| Thermal efficiency | about 79% |
| Heat input at rating | 2.2 MW |
The scope covered the pressure vessel, burner, feedwater pump set, controls and the safety interlock chain. Site work was limited to foundations, flue, water and fuel connections, because the unit arrived assembled and tested.
The mill generates husk only during the harvest and needs steam all year. The measured load profile showed the peak was short and repeatable, so the answer was to make the boiler follow it without losing stability, and to remove the manual compensation the operators had invented. Commissioning included a 72-hour run at the real pattern, with the combustion curve trimmed at four firing rates.
After handover, a 400 m2 covered store plus briquetting of the surplus kept the boiler on husk for eleven months of the year. The plant logs header pressure and stack temperature every two hours, which is enough to catch fouling and load drift before either becomes a shutdown.
Comparable installations are listed under project cases, and the equipment is described on the product page. Fuel and water treatment choices for this kind of site are covered in the industry solutions section.
External links open the publisher’s website and are provided for background reading.
The measured fifteen-minute peak was covered by 3 t/h with a 10% margin. A larger unit would have run below its stable minimum for most of the day, which costs more in part-load losses than it saves in peak headroom.
Seven days on site for this size, including hydraulic test, boil-out, steam blowing, safety-valve setting and a 72-hour run at the plant's real load pattern.
We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.