Capacity · fuel cost · market price
Pick the boiler by the tonne, not by the brochure
Industrial boilers are sold by output — tonnes of steam per hour. This guide works the other way round: start from the steam your plant actually needs, then read the fuel bill and the equipment price for that exact size.



How capacity converts
Every figure on this site that mentions tonnes refers to this definition: saturated steam at the rated pressure, measured at the boiler outlet. If a supplier quotes “1 ton” as 1,000 kg of steam at a different feedwater temperature, the fuel numbers will not line up.
The ladder we cover
Sixteen sizes from half a tonne to fifty tonnes per hour. The engineering decision changes at each step: packaged versus assembled, fire-tube versus water-tube, single boiler versus a pair. Pick the size closest to your peak, then read the fuel bill for that exact output.
0.5 tonnes per hour
0.5 t/h steam boiler
Half a tonne per hour is 500 kg of steam an hour — 0.35 MW, or 300,000 kcal/h. Below this output the packaged horizontal shell stops making sense and the market splits into vertical…
- Steam output
- 500 kg/h
- Thermal
- 0.35 MW
- Gas package
- $6k–$10k
- Biomass package
- $9k–$14k
1 tonnes per hour
1 t/h steam boiler
One tonne per hour — 1,000 kg/h, 0.7 MW, 600,000 kcal/h — is the most common first industrial boiler in the world. It ships as a single packaged unit, fits in a 20-foot container,…
- Steam output
- 1,000 kg/h
- Thermal
- 0.70 MW
- Gas package
- $9k–$15k
- Biomass package
- $15k–$22k
2 tonnes per hour
2 t/h steam boiler
Two tonnes per hour is the workhorse of the industrial range: 2,000 kg/h, about 1.4 MW. It is the size most often bought second-hand and most often rebuilt, because the shell is simple enough…
- Steam output
- 2,000 kg/h
- Thermal
- 1.40 MW
- Gas package
- $15k–$24k
- Biomass package
- $22k–$33k
3 tonnes per hour
3 t/h steam boiler
Three tonnes per hour — 3,000 kg/h, 2.1 MW — is where a plant stops being small. The unit is still packaged, still ships in one piece, but the ancillary scope now includes a…
- Steam output
- 3,000 kg/h
- Thermal
- 2.10 MW
- Gas package
- $21k–$33k
- Biomass package
- $30k–$45k
4 tonnes per hour
4 t/h steam boiler
Four tonnes per hour produces 4,000 kg/h of steam, about 2.8 MW. It is still a single packaged shell — the largest that travels comfortably as one piece — and it is the size…
- Steam output
- 4,000 kg/h
- Thermal
- 2.80 MW
- Gas package
- $28k–$44k
- Biomass package
- $40k–$58k
5 tonnes per hour
5 t/h steam boiler
Five tonnes per hour — 5,000 kg/h, 3.5 MW — sits at the top of the packaged fire-tube range that most plants buy. Above it, water-tube designs start to compete on footprint and part-load…
- Steam output
- 5,000 kg/h
- Thermal
- 3.50 MW
- Gas package
- $34k–$52k
- Biomass package
- $47k–$68k
6 tonnes per hour
6 t/h steam boiler
Six tonnes per hour — 6,000 kg/h, about 4.2 MW — is the point where packaged fire-tube designs meet their practical limit and water-tube designs start to make sense. Both are quoted at this…
- Steam output
- 6,000 kg/h
- Thermal
- 4.20 MW
- Gas package
- $40k–$62k
- Biomass package
- $58k–$84k
8 tonnes per hour
8 t/h steam boiler
Eight tonnes per hour — 8,000 kg/h, 5.6 MW — is the fork in the road. Both fire-tube and water-tube designs are quoted at this size, and the choice follows the load profile more…
- Steam output
- 8,000 kg/h
- Thermal
- 5.60 MW
- Gas package
- $54k–$82k
- Biomass package
- $78k–$112k
10 tonnes per hour
10 t/h steam boiler
Ten tonnes per hour — 10,000 kg/h, about 7 MW — is the entry point to utility-style operation. The unit is normally water-tube, delivered in sections, and the plant around it now includes a…
- Steam output
- 10,000 kg/h
- Thermal
- 7.00 MW
- Gas package
- $67k–$102k
- Biomass package
- $96k–$138k
12 tonnes per hour
12 t/h steam boiler
Twelve tonnes per hour is a water-tube size. Output is 12,000 kg/h, roughly 8.4 MW, and the boiler is delivered as a D-type or double-drum unit in shipping sections rather than as one packaged…
- Steam output
- 12,000 kg/h
- Thermal
- 8.40 MW
- Gas package
- $86k–$128k
- Biomass package
- $118k–$168k
15 tonnes per hour
15 t/h steam boiler
Fifteen tonnes per hour — 10.5 MW — is the smallest size where plants normally specify a deaerator as standard rather than as an option. At this output the feedwater oxygen budget matters to…
- Steam output
- 15,000 kg/h
- Thermal
- 10.50 MW
- Gas package
- $104k–$155k
- Biomass package
- $142k–$198k
20 tonnes per hour
20 t/h steam boiler
Twenty tonnes per hour produces 20,000 kg/h of steam, about 14 MW. It is a utility-scale package: two-drum or D-type water-tube, forced or balanced draft, and a control system that talks to the plant…
- Steam output
- 20,000 kg/h
- Thermal
- 14.00 MW
- Gas package
- $136k–$202k
- Biomass package
- $175k–$245k
25 tonnes per hour
25 t/h steam boiler
Twenty-five tonnes per hour — 17.5 MW — is normally the first boiler in a plant that distributes steam across several buildings. That changes the specification: pressure has to hold at the far end…
- Steam output
- 25,000 kg/h
- Thermal
- 17.50 MW
- Gas package
- $168k–$248k
- Biomass package
- $205k–$290k
30 tonnes per hour
30 t/h steam boiler
Thirty tonnes per hour, about 21 MW, sits at the top of the packaged water-tube range before designs move to field-erected utility boilers. Most units at this size are D-type with a single drum…
- Steam output
- 30,000 kg/h
- Thermal
- 21.00 MW
- Gas package
- $198k–$292k
- Biomass package
- $240k–$335k
40 tonnes per hour
40 t/h steam boiler
Forty tonnes per hour — 28 MW — is field-erected territory. The pressure part arrives in panels and drums, is assembled on a prepared foundation, and the erection sequence is planned before the purchase…
- Steam output
- 40,000 kg/h
- Thermal
- 28.00 MW
- Gas package
- $258k–$380k
- Biomass package
- $305k–$430k
50 tonnes per hour
50 t/h steam boiler
Fifty tonnes per hour produces 35 MW of thermal output. It is usually part of a cogeneration or utility scheme rather than a stand-alone boiler, and it is specified alongside turbines, let-down stations and…
- Steam output
- 50,000 kg/h
- Thermal
- 35.00 MW
- Gas package
- $315k–$465k
- Biomass package
- $370k–$520k
What moves the price of a tonne of steam
Fuel
Gas at 0.46 USD/Nm³ and biomass pellets at 0.16 USD/kg land within 25% of each other per tonne of steam. Coal is cheapest per tonne but carries handling, ash and permitting costs that the fuel price hides.
Efficiency
Each percentage point of thermal efficiency is worth about 1% of the fuel bill. An economiser typically returns two to three points; a condensing recovery unit on gas returns more, if the low-grade heat can be used.
Load profile
A boiler at 40% load burns more per tonne than the same boiler at 80%. Sizing to the base load and letting a smaller unit take the peaks often beats one large unit sized to the peak.
How to use this guide
- Find your size. Take the highest hourly steam draw, add 15% for blowdown and standby, and round up to the nearest size on the ladder.
- Read the fuel line. Each size page prices gas, diesel, biomass and coal per hour and per tonne, at stated calorific values.
- Compare the price map. Equipment-only, packaged skid and turnkey numbers are separated, because most misleading quotes mix the three.
Not sure which size?
Send the steam pressure, the hourly demand and the fuel you expect to burn. We will come back with the size, the fuel bill per tonne and a price band for that configuration.