View details10 t/h coal steam boiler at 1.6 MPa on coal, commissioned in 2020 in Poznań, Poland: the network load collapses in the shoulder season and one large unit could not follow it.

10 t/h at 1.6 MPa, fired on coal, was commissioned in 2020 for a district heating plant in Poznań. The network load collapses in the shoulder season and one large unit could not follow it. The fix was a SZL series unit selected on the measured load, not on the nominal process rating.
The plant needed a different working point, not a bigger version of the same unit. The specification was rewritten around the process instead of a catalogue rating. The site runs three shifts and the steam demand is set by batch equipment rather than by a continuous process, so the load curve has a sharp morning peak and a long plateau.
| Item | Value |
|---|---|
| Model | SZL series, 10 t/h |
| Working pressure | 1.6 MPa |
| Fuel | coal |
| Full-load fuel demand | 1.93 t/h |
| Thermal efficiency | about 79% |
| Heat input at rating | 7.2 MW |
The scope covered the pressure vessel, burner, feedwater pump set, controls and the safety interlock chain. Site work was limited to foundations, flue, water and fuel connections, because the unit arrived assembled and tested.
The network load collapses in the shoulder season and one large unit could not follow it. The measured load profile showed the peak was short and repeatable, so the answer was to make the boiler follow it without losing stability, and to remove the manual compensation the operators had invented. Commissioning included a 72-hour run at the real pattern, with the combustion curve trimmed at four firing rates.
After handover, a smaller lead boiler plus the existing unit in standby cut coal use by 11% in the transition months. The plant logs header pressure and stack temperature every two hours, which is enough to catch fouling and load drift before either becomes a shutdown.
Comparable installations are listed under project cases, and the equipment is described on the product page. Fuel and water treatment choices for this kind of site are covered in the industry solutions section.
External links open the publisher’s website and are provided for background reading.
The measured fifteen-minute peak was covered by 10 t/h with a 10% margin. A larger unit would have run below its stable minimum for most of the day, which costs more in part-load losses than it saves in peak headroom.
Seven days on site for this size, including hydraulic test, boil-out, steam blowing, safety-valve setting and a 72-hour run at the plant's real load pattern.