View detailsA 1.5 t/h biomass boiler on coffee husk and wood waste supplies pasteurisation and CIP steam at a dairy near Kampala, with a simple, locally maintainable design.

The dairy collects about 25,000 litres of milk a day from smallholders north of Kampala and pasteurises it for the local market. Steam for the pasteuriser and the CIP set used to come from a diesel-fired boiler, and fuel was the plant’s second-largest cost after milk. The replacement is a 1.5 t/h biomass boiler at 0.8 MPa, burning coffee husk and wood waste from a nearby sawmill.
The load is modest: 0.6-0.9 t/h for pasteurisation, rising to 1.2 t/h for 30 minutes during CIP. The boiler is sized on the CIP peak, not on the average.
Uganda produces coffee husk in quantity, and it is cheap but awkward: bulk density around 250 kg/m3, moisture 12-18%, and a tendency to bridge in hoppers. The boiler’s furnace is a chain grate with a tall arch, and the fuel feeder is a wide belt rather than a screw, because a screw bridges with husk.
At 1.5 t/h the boiler absorbs about 1.0 MW. On a 14 MJ/kg husk/wood mix the fuel rate is about 330 kg/h, which the plant buys for a fraction of the diesel it replaced.
| Item | Value |
|---|---|
| Rated evaporation | 1.5 t/h |
| Pressure | 0.8 MPa |
| Fuel | coffee husk with wood waste |
| Fuel rate at rating | about 330 kg/h |
| Efficiency | about 76% |
| Dust control | multi-cyclone |
The plant has one boiler operator and no instrument technician. The control system is a relay-based burner management panel with a small PLC for feedwater and grate speed, chosen because local electricians can repair it. The plant keeps spare grate bars, a flame scanner and a feedwater pump on site.
Water treatment is a softener and a simple chemical dosing set. The dairy’s water is soft enough that hardness is not the main issue; the plant’s problem was organic matter in the borehole water during the rainy season, which fouled the softener. A chlorine dose ahead of the softener and a carbon filter fixed it.
The dairy’s steam cost fell by more than half, and the boiler has run two years on husk with one planned grate rebuild. Pasteurisation holds 75 °C through the holding tube, and the CIP set reaches 80 °C in 25 minutes. The plant’s next step is a small economizer, which it expects to pay back in about 18 months at current husk prices.
External links open the publisher’s website and are provided for background reading.
Yes, with a wide feeder and a tall furnace arch. Husk is light and bridges easily, so a belt feeder works better than a screw.
CIP draws more steam for a short period than pasteurisation does all day. Sizing on the peak avoids a pressure dip at the end of the shift.
Softening plus oxygen scavenging, with a carbon filter if the borehole water carries organic matter.