Two 3 t/h Gas Steam Boilers for a Food and Seasoning Plant in Lagos, Nigeria

Two 3 t/h gas steam boilers supply cooking, drying and CIP steam at a seasoning plant in Lagos, with N+1 redundancy and a gas train rated for local supply pressure.

4 t/h Gas Steam Boiler for a Food Plant in Sohar, Oman – Yuanda Boiler
Place
Lagos, Nigeria
Industry
Food and seasoning
Equipment
2 x 3 t/h WNS gas steam boilers
Year
2024

Two units, one running, one ready

The seasoning plant in Lagos makes bouillon cubes and packaged spices, and its steam load is 2-2.5 t/h for cooking and drying, with a 2.8 t/h peak when the CIP set runs. Two 3 t/h WNS gas boilers at 1.0 MPa were installed so that one carries the load and the other stands ready, rather than a single 3 t/h unit running flat out.

The plant’s gas arrives at a lower pressure than the burner’s nominal requirement, so the gas train was sized for 15-25 kPa inlet with a booster fan downstream. That single detail decided the burner selection: a standard train would have tripped on low pressure every afternoon.

Load and redundancy

Each boiler absorbs about 2.1 MW at rating. On gas at 34 MJ/Nm3 and 93% efficiency the full-load rate is about 240 Nm3/h. The plant runs one boiler at 70-85% and rotates weekly, which keeps both units exercised and spreads maintenance.

Plant data
Item Value
Installed capacity 2 x 3 t/h
Pressure 1.0 MPa
Average / peak load 2.0-2.5 / 2.8 t/h
Gas inlet pressure 15-25 kPa
Efficiency about 93%
Feedwater softened, deaerated

The gas booster and safety chain

The booster is a dry-running screw compressor with a pressure switch and a non-return valve, installed outdoors under a canopy. The burner management system proves gas pressure, air pressure and flame before each start, and the double-block-and-bleed train is leak-tested daily.

Nigeria’s gas composition varies by supplier, and the plant keeps a quarterly analysis on file. The burner was commissioned on the first analysis and re-trimmed once when the supplier changed; CO stayed under 25 ppm.

Water treatment and steam use

The plant’s borehole water is hard and high in iron. A softener plus an iron filter keeps hardness below 0.03 mmol/L, and the deaerator removes oxygen at 105 °C. Steam is used in jacketed kettles and a rotary dryer, so the plant holds TDS at 2,000 ppm and checks steam dryness at the header monthly.

Results

The plant has run two years without a production stop for boiler reasons, including one period when a boiler was opened for its annual inspection. Gas consumption per tonne of product fell by 11% against the old single boiler, mostly because the plant can now run a unit at a reasonable firing rate instead of cycling a larger one.

Frequently asked questions

Why two 3 t/h boilers for a 2.5 t/h load?

Redundancy and part-load efficiency. One unit covers the load at 70-85% and the other is available for maintenance rotation or a peak.

What if gas pressure is low?

The gas train is sized for 15-25 kPa with a booster fan, so the burner sees stable pressure even when the distribution network sags.

How often should the gas train be leak-tested?

Daily, before first start. The double-block-and-bleed arrangement makes the test a two-minute procedure.

Partners

Become a Yuanda Boiler agent

We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.

Apply as an agent
WhatsApp [email protected]
Call WhatsApp Email Get a quote