
1-100 t/h (0.7-70 MW)
WNS Gas/Oil Steam Boiler, 1-100 t/h
Packaged three-pass wet-back fire-tube steam boiler for gas and oil, 1-100 t/h at 1.25 MPa, with matched modulating burner and ful...
View details3 t/h gas steam boiler at 1.0 MPa on natural gas, commissioned in 2024 in Querétaro, Mexico: the paint shop needs steam at 07:00 sharp and the boiler was started cold at 06:20.

3 t/h at 1.0 MPa, fired on natural gas, was commissioned in 2024 for a automotive parts plant in Querétaro. The paint shop needs steam at 07:00 sharp and the boiler was started cold at 06:20. The fix was a WNS series unit selected on the measured load, not on the nominal process rating.
The plant needed a different working point, not a bigger version of the same unit. The specification was rewritten around the process instead of a catalogue rating. The site runs three shifts and the steam demand is set by batch equipment rather than by a continuous process, so the load curve has a sharp morning peak and a long plateau.
| Item | Value |
|---|---|
| Model | WNS series, 3 t/h |
| Working pressure | 1.0 MPa |
| Fuel | natural gas |
| Full-load fuel demand | 232 Nm3/h |
| Thermal efficiency | about 94% |
| Heat input at rating | 2.2 MW |
The scope covered the pressure vessel, burner, feedwater pump set, controls and the safety interlock chain. Site work was limited to foundations, flue, water and fuel connections, because the unit arrived assembled and tested.
The paint shop needs steam at 07:00 sharp and the boiler was started cold at 06:20. The measured load profile showed the peak was short and repeatable, so the answer was to make the boiler follow it without losing stability, and to remove the manual compensation the operators had invented. Commissioning included a 72-hour run at the real pattern, with the combustion curve trimmed at four firing rates.
After handover, a scheduled warm-up and a hot standby at 40% load removed the cold start and the shop opens on temperature. The plant logs header pressure and stack temperature every two hours, which is enough to catch fouling and load drift before either becomes a shutdown.
Comparable installations are listed under project cases, and the equipment is described on the product page. Fuel and water treatment choices for this kind of site are covered in the industry solutions section.
External links open the publisher’s website and are provided for background reading.
The measured fifteen-minute peak was covered by 3 t/h with a 10% margin. A larger unit would have run below its stable minimum for most of the day, which costs more in part-load losses than it saves in peak headroom.
Seven days on site for this size, including hydraulic test, boil-out, steam blowing, safety-valve setting and a 72-hour run at the plant's real load pattern.
We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.