Capacity & Cost guide Industrial boiler manufacturer since 1965 Taikang, Zhoukou, Henan, China
Project case

4 t/h Biomass Steam Boiler for a Palm Oil Mill in Kuching, Malaysia

4 t/h biomass steam boiler at 1.0 MPa on palm kernel shell, commissioned in 2022 in Kuching, Malaysia: shell arrives with sand and the ash handling was manual.

4 t/h Biomass Steam Boiler for a Palm Oil Mill in Kuching, Malaysia – Yuanda Boiler
Place
Kuching, Malaysia
Industry
Palm oil
Equipment
DZL series biomass steam boiler, 4 t/h at 1.0 MPa
Year
2022

4 t/h at 1.0 MPa, fired on palm kernel shell, was commissioned in 2022 for a palm oil plant in Kuching. Shell arrives with sand and the ash handling was manual. The fix was a DZL series unit selected on the measured load, not on the nominal process rating.

The plant

The plant needed a different working point, not a bigger version of the same unit. The specification was rewritten around the process instead of a catalogue rating. The site runs two shifts and the steam demand is set by batch equipment rather than by a continuous process, so the load curve has a sharp morning peak and a long plateau.

What was specified

Item Value
Model DZL series, 4 t/h
Working pressure 1.0 MPa
Fuel palm kernel shell
Full-load fuel demand 1 kg/h
Thermal efficiency about 79%
Heat input at rating 2.9 MW

The scope covered the pressure vessel, burner, feedwater pump set, controls and the safety interlock chain. Site work was limited to foundations, flue, water and fuel connections, because the unit arrived assembled and tested.

How it runs

Shell arrives with sand and the ash handling was manual. The measured load profile showed the peak was short and repeatable, so the answer was to make the boiler follow it without losing stability, and to remove the manual compensation the operators had invented. Commissioning included a 72-hour run at the real pattern, with the combustion curve trimmed at four firing rates.

Result

After handover, a moving grate with an ash conveyor took the grit and cut ash handling labour from two shifts to one. The plant logs header pressure and stack temperature every two hours, which is enough to catch fouling and load drift before either becomes a shutdown.

Comparable installations are listed under project cases, and the equipment is described on the product page. Fuel and water treatment choices for this kind of site are covered in the industry solutions section.

Frequently asked questions

Why 4 t/h and not the next size up?

The measured fifteen-minute peak was covered by 4 t/h with a 10% margin. A larger unit would have run below its stable minimum for most of the day, which costs more in part-load losses than it saves in peak headroom.

How long did commissioning take?

Seven days on site for this size, including hydraulic test, boil-out, steam blowing, safety-valve setting and a 72-hour run at the plant's real load pattern.

Partners

Become a Yuanda Boiler agent

We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.

Apply as an agent
WhatsApp [email protected]
Call WhatsApp Email Get a quote