Capacity & Cost guide Industrial boiler manufacturer since 1965 Taikang, Zhoukou, Henan, China
Industry solution

Process Heat for Chemical and Pharmaceutical Plants

Matching steam pressure and thermal oil to reactor, reboiler and dryer duty, with a worked 6 t/h distillation and evaporation example.

3 t/h Gas Steam Boiler for an Automotive Parts Plant in Querétaro, Mexico – Yuanda Boiler

Process heat demand: temperature levels, not tonnage

Chemical and pharmaceutical plants buy heat at a temperature, and the temperature decides the equipment. Jacketed reactors and reboilers running at 140-160 °C are served by steam at 0.6-1.0 MPa. Distillation under pressure, or a reaction held at 200-240 °C, needs 1.6-2.5 MPa saturated steam, or thermal oil if the pressure vessel would otherwise become the most expensive item in the plant. Above about 250 °C, saturated steam needs more than 4 MPa, and thermal oil becomes the cheaper route.

The demand pattern is batch. A reactor heats its jacket, holds, refluxes, cools and discharges; the steam load steps rather than ramps. Two or three vessels coming to temperature together set the boiler size, and the coincidence depends on the batch schedule rather than on the equipment list.

Pharmaceutical plants add a second, smaller demand that is easy to overlook: clean steam for sterilisation, SIP and humidification. It is generated separately from treated water, because the boiler’s amine and oxygen scavenger must not reach a product contact surface.

The equipment train

Up to about 20 t/h at 1.25 MPa, a packaged fire-tube boiler is the economical choice. Above that, or where 1.6-2.5 MPa is required, the water-tube SZS series from 6 to 30 t/h is the usual selection: membrane-wall furnace, top-supported, and a steam drum large enough to absorb batch steps without priming.

Around the boiler the scope is set by water quality rather than by steam quantity. Demineralised or reverse-osmosis make-up allows blowdown at 1-2% instead of 5%, which matters at 1.6 MPa where each percent of blowdown carries real energy. A deaerator, stainless condensate lines and a blowdown flash vessel complete the train. For 300 °C process duty, a YY(Q)W thermal oil heater replaces the high-pressure boiler entirely.

Parameter Value Note
Installed steam capacity 2 × 8 t/h at 1.6 MPa one duty, one standby
Steam temperature 204 °C saturated, 1.6 MPa
Peak process demand 6.2 t/h reboiler plus evaporator
Feedwater 105 °C, demineralised deaerator outlet
Blowdown 2% low solids make-up
Clean steam 500 kg/h separate generator, RO feed
Design efficiency 95% (LHV) economiser and air preheater

Worked example: reboiler, evaporator and dryer on one header

A solvent recovery column takes 4,200 kg/h of distillate at a reflux ratio of 2.5, so the vapour rate at the top is 4,200 × 3.5 = 14,700 kg/h. With a latent heat of 380 kJ/kg, the reboiler duty is 14,700 × 380 = 5.59 GJ/h, or 1,552 kW.

Beside it, an evaporator removes 2,000 kg/h of water and uses 1.15 kg of steam per kilogramme evaporated, which is 2.3 t/h of steam, or 2.3 × 2,352 MJ/t = 5.41 GJ/h = 1,502 kW. A tray dryer adds 800 kW.

Total 3,854 kW. Add 5% for line losses and the occasional fourth user, and the header must supply 4.05 MW, which at 2,352 kJ/kg is 6.2 t/h. The next standard size is 8 t/h, so the plant takes two of them: one duty at 78% of rating, one standby. That is what a batch plant with a single column usually wants, because losing the column for a boiler repair costs more than the second shell.

Check the pressure level before fixing 1.6 MPa. If the reboiler runs at 150 °C, steam at 1.0 MPa gives 180 °C and a 30 K approach; 1.6 MPa only earns its place if a reactor or steriliser needs 200 °C. Choosing the lower level reduces the pressure-vessel cost of every item on the header, the boiler included.

Efficiency, operating cost and compliance

Where the money is

Blowdown at 1.6 MPa carries about 774 kJ per kilogramme above cold make-up, so 5% blowdown costs roughly 1.6% of the fuel and 2% costs about 0.7%. Flash recovery from continuous blowdown to the deaerator recovers part of that, and on a demineralised plant the rest is the price of protecting the drum.

Condensate return is the second lever. A chemical plant can usually return 80% at 90-100 °C, and each 10% of return replaces make-up that would otherwise be heated from 20 °C and treated from scratch. The third lever is part-load sequencing: with two units, run one at high fire and start the second only when the first passes 85%, rather than running both at half load where fixed losses dominate.

Emissions and compliance

NOx limits of 30-50 mg/Nm³ are normal for gas firing in industrial zones and are met with flue-gas recirculation and a matched burner. Where the process handles solvents, the boiler house electrical classification and the combustion air intake position need checking against the site’s hazardous-area drawing; a boiler drawing air from a solvent-laden atmosphere is a safety issue, not an emissions one.

The steam system itself is a compliance item in pharmaceutical plants. Clean steam is generated from RO water in a dedicated generator, distributed in stainless steel with sanitary fittings, and monitored for conductivity and non-condensable gases. Boiler steam and clean steam must never share a header.

Specification pitfalls and the data we need

Four mistakes that surface late

  • Specifying 1.25 MPa by habit when two users need 1.6 MPa, then adding a booster that nobody sized.
  • Sizing on the sum of reactor jacket duties without a batch schedule, which overstates the peak by 50% or more.
  • Leaving clean steam out of the enquiry and discovering at commissioning that the boiler cannot feed a sanitary generator.
  • Returning condensate from reactors and dryers that carry product, which contaminates the whole hotwell.

The user list we need

  • Each steam user with its duty in kW or kg/h, pressure, temperature and batch duration.
  • The batch schedule, so coincidence can be tested rather than assumed.
  • Required steam purity and whether clean steam is needed.
  • Make-up water analysis and the treatment scheme already installed.
  • Fuel, and whether a dual-fuel burner is required for security of supply.
  • Plot space, indoor or outdoor installation, and the local emissions and noise limits.

With the user list and the batch schedule we can produce a load duration curve, size the units and set the pressure level once for the whole header.

Frequently asked questions

When should a chemical plant use thermal oil instead of steam?

Above roughly 250-260 °C, or when the duty needs a high temperature at low pressure. Thermal oil at 300 °C runs at 0.6-1.0 MPa, so the heater, pipework and coils stay simple, while saturated steam at 300 °C would need over 8 MPa and a very different class of equipment.

How much standby capacity does a batch chemical plant need?

Usually one full unit, so that a single failure does not stop the column or the reactor train. For a 6.2 t/h peak that means two 8 t/h units: one duty at 78% load, one standby, which also leaves room for a process step that grows.

Can boiler steam be used for sterilisation?

Not directly for product-contact surfaces. Sterilisation steam should come from a clean steam generator fed with RO water and no volatile treatment chemicals. Boiler steam can serve jackets, reboilers and air heaters through exchangers.

What blowdown rate is realistic with demineralised make-up?

1-2% is typical, against 5% with softened water. The limit is usually silica or conductivity in the drum rather than hardness, and automatic conductivity control holds it there without operator intervention.

Partners

Become a Yuanda Boiler agent

We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.

Apply as an agent
WhatsApp [email protected]
Call WhatsApp Email Get a quote