Two 2.8 MW Gas Hot Water Boilers for a Hotel Complex in Samarkand

Two 2.8 MW gas hot water boilers at 95/70 C serve a 320-room hotel complex in Samarkand, with domestic hot water priority and a weather-compensated curve.

Two 2.8 MW Gas Hot Water Boilers for a Hotel Complex in Samarkand – Yuanda Boiler
Place
Samarkand, Uzbekistan
Industry
Hotels and hospitality
Equipment
2 x 2.8 MW WNS gas hot water boilers
Year
2024

Heating, hot water and a lot of guests

The hotel complex in Samarkand has 320 rooms, a spa, two restaurants and a conference wing. Heating runs on a 95/70 °C circuit through fan-coil units and radiators, and domestic hot water is produced in two plate heat exchangers fed from a 60 m3 storage tank. The two loads peak at different times: heating in the early morning, hot water in the evening.

Two 2.8 MW gas hot water boilers cover both. Each is a WNS fire-tube hot water boiler with a three-pass wet-back design, and the pair is sized so one unit carries the summer hot-water load alone while both run in winter.

Why two smaller units

A single 5.6 MW boiler would have been marginally cheaper, but a hotel cannot lose heat for a week while a boiler is repaired. The two-unit arrangement gives N+1 redundancy at part load: in summer one boiler runs at 30-40% on hot water, and in winter both run at 60-70%. The plant also keeps the old diesel boiler as a third standby for the coldest week.

The boilers are on a common header with primary pumps and a hydraulic separator, so the secondary circuits see a stable differential pressure regardless of which boiler is running.

Design data
Item Value
Installed capacity 2 x 2.8 MW
Heating circuit 95 / 70 °C
Domestic hot water 60 °C from storage
Rooms served 320 plus spa and restaurants
Efficiency about 93%
Fuel natural gas

Controls and the shoulder season

The plant runs a weather-compensated heating curve with night setback, and the hot-water loop has priority: if the storage tank falls below 45 °C, the heating circuit is temporarily reduced. That logic matters in spring and autumn, when heating demand is low but hot-water demand is normal.

Samarkand’s water is moderately hard, so the hot-water side is filled with softened water and the make-up is metered. The boilers themselves see treated water with a conductivity limit, and the plant logs gas and make-up weekly.

What the hotel notices

Guest complaints about hot water dropped to nil in the first season, and the heating holds 22 °C in rooms through a -8 °C night. Gas use in the first year was 6% below the old plant’s, mostly from running one boiler in summer instead of a large unit at low fire.

Frequently asked questions

Why not one 5.6 MW boiler?

Redundancy and part-load efficiency. One boiler carries the summer hot-water load at a reasonable firing rate, and the hotel is never without heat during maintenance.

How is domestic hot water prioritised?

A storage tank with a temperature sensor gives the DHW loop priority; if tank temperature falls below 45 C the heating circuit is temporarily reduced.

What water treatment is needed?

Softened make-up for the hot-water circuit and conductivity-controlled boiler water. Hard make-up will scale the heat exchangers before it affects the boiler.

Partners

Become a Yuanda Boiler agent

We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.

Apply as an agent
WhatsApp [email protected]
Call WhatsApp Email Get a quote