View detailsA 10 t/h water-tube biomass boiler supplies a garment complex in Hawassa Industrial Park, with a fuel yard, bag filter and a steam header shared by three factories.

Hawassa Industrial Park groups garment factories under a common utility model, and this complex has three tenants sharing a 10 t/h steam header. The boiler is a water-tube SZL unit at 1.6 MPa, 10 t/h, firing eucalyptus chips and wood waste from the park’s own furniture tenants.
Sharing steam is a control problem as much as a boiler problem: each tenant draws what it needs, and the header pressure is the only common signal. The plant runs the boiler on header-pressure control with a feedforward signal from the largest tenant’s dye-house schedule.
At 10 t/h and 1.6 MPa the water-tube design gives a larger furnace for the fuel’s volatile content and a faster response to load changes than a fire-tube unit of the same rating. The SZL is an assembled chain-grate boiler: it ships in modules and is erected on site, which suited a park where the boiler house was built after the boiler was ordered.
At rating the unit absorbs about 7 MW. On a 13.5 MJ/kg chip mix the fuel rate is about 1.9 t/h, and the park’s fuel yard can hold five days of chips under cover.
| Item | Value |
|---|---|
| Rated evaporation | 10 t/h |
| Pressure | 1.6 MPa |
| Fuel | eucalyptus chips, wood waste |
| Fuel rate at rating | about 1.9 t/h |
| Efficiency | about 80% |
| Dust control | multi-cyclone plus bag filter |
The park’s furniture factories produce offcuts that used to be dumped, and the boiler now takes them. The chips are delivered by tractor and tipped into a covered bay; a front-end loader feeds the grate hopper. The plant tests moisture weekly and rejects loads above 30%, because wet chips cut capacity and raise the stack temperature.
The ash is sold to a block maker outside Hawassa. At 1.9 t/h fuel and 4% ash, the boiler produces about 1.8 t of ash a day, which is a truckload every three days.
Erection took twelve weeks and commissioning nine days. The first month exposed a tenant-coordination issue rather than an equipment one: one factory opened its dye-house valves simultaneously at shift start, dropping header pressure by 0.15 MPa. The fix was a pressure-control valve at each tenant’s take-off and a shift-start schedule staggered by 20 minutes.
The boiler now holds 1.55 MPa at the header through the working day, and the park reports that steam cost per garment is about 30% below the diesel-fired baseline.
External links open the publisher’s website and are provided for background reading.
Yes, with a common header, pressure-control valves at each take-off and a staggered start schedule so simultaneous draws do not collapse header pressure.
Larger furnace volume, faster load response and better tolerance of high-volatile biomass. It also ships as modules for site erection.
About 1.9 t/h of 13.5 MJ/kg chips at rating, or roughly 40 t a day over a 22-hour run.