
6-100 t/h
SZS Water-Tube Gas/Oil Steam Boiler, 6-100 t/h
Membrane-wall water-tube steam boiler with staged combustion and FGR, 6-100 t/h at up to 2.5 MPa and 98% efficiency with heat reco...
View details6 t/h coal steam boiler at 1.6 MPa on coal, commissioned in 2021 in Durban, South Africa: the plant had to keep steam during a three-week gas interruption.

6 t/h at 1.6 MPa, fired on coal, was commissioned in 2021 for a chemical plant in Durban. The plant had to keep steam during a three-week gas interruption. The fix was a SZL series unit selected on the measured load, not on the nominal process rating.
The plant was running a boiler that had been sized for a different process. The operating team had learned to work around it: start earlier, raise the setpoint, accept the dip. The site runs one extended shift and the steam demand is set by batch equipment rather than by a continuous process, so the load curve has a sharp morning peak and a long plateau.
| Item | Value |
|---|---|
| Model | SZL series, 6 t/h |
| Working pressure | 1.6 MPa |
| Fuel | coal |
| Full-load fuel demand | 1.16 t/h |
| Thermal efficiency | about 79% |
| Heat input at rating | 4.3 MW |
The scope covered the pressure vessel, burner, feedwater pump set, controls and the safety interlock chain. Site work was limited to foundations, flue, water and fuel connections, because the unit arrived assembled and tested.
The plant had to keep steam during a three-week gas interruption. The measured load profile showed the peak was short and repeatable, so the answer was to make the boiler follow it without losing stability, and to remove the manual compensation the operators had invented. Commissioning included a 72-hour run at the real pattern, with the combustion curve trimmed at four firing rates.
After handover, dual coal and gas capability carried production through the interruption and the coal side now runs two weeks a year as a test. The plant logs header pressure and stack temperature every two hours, which is enough to catch fouling and load drift before either becomes a shutdown.
Comparable installations are listed under project cases, and the equipment is described on the product page. Fuel and water treatment choices for this kind of site are covered in the industry solutions section.
External links open the publisher’s website and are provided for background reading.
The measured fifteen-minute peak was covered by 6 t/h with a 10% margin. A larger unit would have run below its stable minimum for most of the day, which costs more in part-load losses than it saves in peak headroom.
Seven days on site for this size, including hydraulic test, boil-out, steam blowing, safety-valve setting and a 72-hour run at the plant's real load pattern.
We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.