4 t/h Gas Steam Boiler for a Beverage Plant in Barranquilla, Colombia

4 t/h gas steam boiler at 1.0 MPa on natural gas, commissioned in 2024 in Barranquilla, Colombia: the plant is on the coast and the boiler casing corroded within two years.

Combined Steam and Hot Water Boiler, 0.5-4 t/h – Yuanda Boiler
Place
Barranquilla, Colombia
Industry
Beverage
Equipment
WNS series gas steam boiler, 4 t/h at 1.0 MPa
Year
2024

4 t/h at 1.0 MPa, fired on natural gas, was commissioned in 2024 for a beverage plant in Barranquilla. The plant is on the coast and the boiler casing corroded within two years. The fix was a WNS series unit selected on the measured load, not on the nominal process rating.

The plant

The plant needed a different working point, not a bigger version of the same unit. The specification was rewritten around the process instead of a catalogue rating. The site runs one extended shift and the steam demand is set by batch equipment rather than by a continuous process, so the load curve has a sharp morning peak and a long plateau.

What was specified

Item Value
Model WNS series, 4 t/h
Working pressure 1.0 MPa
Fuel natural gas
Full-load fuel demand 310 Nm3/h
Thermal efficiency about 94%
Heat input at rating 2.9 MW

The scope covered the pressure vessel, burner, feedwater pump set, controls and the safety interlock chain. Site work was limited to foundations, flue, water and fuel connections, because the unit arrived assembled and tested.

How it runs

The plant is on the coast and the boiler casing corroded within two years. The measured load profile showed the peak was short and repeatable, so the answer was to make the boiler follow it without losing stability, and to remove the manual compensation the operators had invented. Commissioning included a 72-hour run at the real pattern, with the combustion curve trimmed at four firing rates.

Result

After handover, a heavier casing coating and a sealed insulation system stopped the corrosion; the second unit was specified the same way. The plant logs header pressure and stack temperature every two hours, which is enough to catch fouling and load drift before either becomes a shutdown.

Comparable installations are listed under project cases, and the equipment is described on the product page. Fuel and water treatment choices for this kind of site are covered in the industry solutions section.

Frequently asked questions

Why 4 t/h and not the next size up?

The measured fifteen-minute peak was covered by 4 t/h with a 10% margin. A larger unit would have run below its stable minimum for most of the day, which costs more in part-load losses than it saves in peak headroom.

How long did commissioning take?

Seven days on site for this size, including hydraulic test, boil-out, steam blowing, safety-valve setting and a 72-hour run at the plant's real load pattern.

Partners

Become a Yuanda Boiler agent

We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.

Apply as an agent
WhatsApp [email protected]
Call WhatsApp Email Get a quote