Twenty-five tonnes per hour — 17.5 MW — is normally the first boiler in a plant that distributes steam across several buildings. That changes the specification: pressure has to hold at the far end of the header, so 1.6 MPa or 2.5 MPa is common and the control valve strategy matters as much as the boiler.

25 t/h25 × 1,000 kg steam per hour
17.50 MWthermal output
$168k–$248kgas package, indicative

D-class packaged boiler in a cabinet enclosure
D-class packaged boiler in a cabinet enclosure Factory render

Where this size fits

Water-tube construction is universal here. The unit ships in several sections, is erected on site, and is hydraulically tested before refractory work. Expect a longer commissioning window than a packaged boiler — typically four to eight weeks from arrival to first steam.

Correct where the steam network, not a single process, sets demand. If one building dominates the load, a smaller dedicated boiler plus a 25 t/h unit for the network is often more flexible.

Pressure vessel shell on turning rolls in the assembly hall
Pressure vessel shell on turning rolls in the assembly hall
Welding bay with boiler shells and drum sections
Welding bay with boiler shells and drum sections

Load profile check

One shift

8 h/day at 80% load delivers about 160,000 kg of steam a day. Steam demand is concentrated; the boiler starts cold each morning.

Two shifts

16 h/day at 75% average is the usual sweet spot for this size: the unit stays in modulation and avoids a second cold start.

Continuous

24 h at 70–85% load is where the efficiency figures in this page actually hold. Below 50% load, expect the fuel cost per tonne to rise.

Machines at this output

SZS25-1.6-Y(Q)

Gas / oil, D-type water-tube

Pressure
1.6 MPa
Steam temp.
204 °C
Efficiency
94–96%
Indicative
$168k–248k

SZS25-2.5-Y(Q)

Gas / oil, 2.5 MPa

Pressure
2.5 MPa
Steam temp.
226 °C
Efficiency
94–96%
Indicative
$185k–268k

SZL25-1.6-T

Biomass, water-tube

Pressure
1.6 MPa
Steam temp.
204 °C
Efficiency
87–89%
Indicative
$205k–290k

Efficiency ranges assume LHV basis and a clean unit at rated load. Local emission limits may require a low-NOx burner and, on gas, flue-gas recirculation.

What a tonne of steam costs

Basis: 600,000 kcal per tonne of steam at 1.25 MPa with 68 °C feedwater; gas 8,500 kcal/Nm³ at 0.46 USD/Nm³; diesel 10,200 kcal/kg at 0.95 USD/kg; biomass 4,000 kcal/kg at 0.16 USD/kg; coal 5,000 kcal/kg at 0.13 USD/kg. Efficiency 92% gas, 90% diesel, 86% biomass, 82% coal.

Natural gas

$35.29 per tonne · 1,918 Nm³/h · $882/h at full load

Light diesel

$62.09 per tonne · 1,634 kg/h · $1,552/h at full load

Biomass pellet

$27.91 per tonne · 4,360 kg/h · $698/h at full load

Bituminous coal

$19.02 per tonne · 3,659 kg/h · $476/h at full load

At eight hours a day and 300 days a year, the gas line alone is about $2,117,647 a year at full fire. Electricity, water, labour and maintenance are excluded.

Market price map

Equipment only

$168k–$248k

Boiler body, burner, control panel. Excludes feedwater, economiser, water treatment, flue and erection.

Packaged skid

$227k–$372k

Adds feedwater pump set, softener, economiser and the interconnecting pipework on a common frame.

Turnkey

+35–60%

Adds foundation, flue and stack, electrical, insulation, erection, commissioning and performance test.

At 25 t/h the market splits between project-quoted turnkey supply and separate boiler/burner/BOP packages. Turnkey carries a premium but shifts interface risk to the supplier; split packages are cheaper only if you have the engineering capacity to manage them.

Typical duties

  • Pulp and paper mills
  • Large food processing estates
  • Rubber and tyre plants
  • Industrial park steam networks

Specify the steam quality at the battery limit (dryness and carryover) — it is a water-treatment and drum-internals question, not a boiler-brand question.

Questions buyers ask at this size

What does a 25 t/h steam boiler cost?

Indicative 2026 EXW range: $168k–$248k for a gas/oil packaged unit, $205k–$290k for a biomass chain-grate unit. Pressure, burner class, economiser and auxiliary scope move the figure by 20–40%.

How much gas does a 25 t/h boiler burn per hour?

About 1,918 Nm³/h at full load, assuming 8,500 kcal/Nm³ and 92% thermal efficiency. That is roughly $882 per hour at 0.46 USD/Nm³.

How long does a 25 t/h unit take to erect?

Typically six to ten weeks from arrival on site, including assembly, refractory, hydraulic test and commissioning, assuming foundations and utilities are ready. Winter conditions and crane availability are the usual causes of slippage.

What is 25 t/h in MW and kcal per hour?

25 t/h is about 17.50 MW, 15,000,000 kcal/h, or roughly 1,600 boiler horsepower.

Sources and further reading

Fuel prices and efficiencies are stated assumptions for comparison, not quotations. Local fuel quality, altitude, feedwater temperature and part-load operation all shift the real number.

Request a quote

Tell us the capacity, fuel and working pressure. Our engineers reply with a technical proposal within one working day.

Or email [email protected] directly.

Partners

Become a Yuanda Boiler agent

We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.

Apply as an agent
WhatsApp [email protected]
Call WhatsApp Email Get a quote