Forty tonnes per hour — 28 MW — is field-erected territory. The pressure part arrives in panels and drums, is assembled on a prepared foundation, and the erection sequence is planned before the purchase order is placed. Site welding, non-destructive testing and hydraulic test are all part of the scope.

40 t/h40 × 1,000 kg steam per hour
28.00 MWthermal output
$258k–$380kgas package, indicative

D-class packaged boiler in a cabinet enclosure
D-class packaged boiler in a cabinet enclosure Factory render

Where this size fits

At this output, a one-point efficiency gain is worth real money: at 8,000 operating hours a year, each percentage point on a 40 t/h gas boiler is roughly 300,000 Nm³ of gas. That is why guarantees, not list prices, decide these projects.

For base-load utility duty in a plant that runs above 30 t/h most of the year. Anything less and a smaller unit plus a standby is more economic.

Pressure vessel shell on turning rolls in the assembly hall
Pressure vessel shell on turning rolls in the assembly hall
Control panel inspection before factory testing
Control panel inspection before factory testing

Load profile check

One shift

8 h/day at 80% load delivers about 256,000 kg of steam a day. Steam demand is concentrated; the boiler starts cold each morning.

Two shifts

16 h/day at 75% average is the usual sweet spot for this size: the unit stays in modulation and avoids a second cold start.

Continuous

24 h at 70–85% load is where the efficiency figures in this page actually hold. Below 50% load, expect the fuel cost per tonne to rise.

Machines at this output

SZS40-1.6-Y(Q)

Gas / oil, D-type water-tube

Pressure
1.6 MPa
Steam temp.
204 °C
Efficiency
94–96%
Indicative
$258k–380k

SZS40-2.5-Y(Q)

Gas / oil, 2.5 MPa

Pressure
2.5 MPa
Steam temp.
226 °C
Efficiency
94–96%
Indicative
$282k–412k

SZL40-1.6-T

Biomass, water-tube

Pressure
1.6 MPa
Steam temp.
204 °C
Efficiency
87–89%
Indicative
$305k–430k

Efficiency ranges assume LHV basis and a clean unit at rated load. Local emission limits may require a low-NOx burner and, on gas, flue-gas recirculation.

What a tonne of steam costs

Basis: 600,000 kcal per tonne of steam at 1.25 MPa with 68 °C feedwater; gas 8,500 kcal/Nm³ at 0.46 USD/Nm³; diesel 10,200 kcal/kg at 0.95 USD/kg; biomass 4,000 kcal/kg at 0.16 USD/kg; coal 5,000 kcal/kg at 0.13 USD/kg. Efficiency 92% gas, 90% diesel, 86% biomass, 82% coal.

Natural gas

$35.29 per tonne · 3,069 Nm³/h · $1,412/h at full load

Light diesel

$62.09 per tonne · 2,614 kg/h · $2,484/h at full load

Biomass pellet

$27.91 per tonne · 6,977 kg/h · $1,116/h at full load

Bituminous coal

$19.02 per tonne · 5,854 kg/h · $761/h at full load

At eight hours a day and 300 days a year, the gas line alone is about $3,388,235 a year at full fire. Electricity, water, labour and maintenance are excluded.

Market price map

Equipment only

$258k–$380k

Boiler body, burner, control panel. Excludes feedwater, economiser, water treatment, flue and erection.

Packaged skid

$348k–$570k

Adds feedwater pump set, softener, economiser and the interconnecting pipework on a common frame.

Turnkey

+35–60%

Adds foundation, flue and stack, electrical, insulation, erection, commissioning and performance test.

These projects are procured as engineering packages. Expect separate scope for boiler, burner, BOP, civil, erection and commissioning, with performance tests at 100% and 75% load before acceptance.

Typical duties

  • Refineries and petrochemical utilities
  • Large pulp mills
  • Steel rolling and heat treatment
  • Urban district heating

Insist on a written erection sequence and a site supervision scope; the interface between civil works and the pressure part is where schedules slip.

Questions buyers ask at this size

What does a 40 t/h steam boiler cost?

Indicative 2026 EXW range: $258k–$380k for a gas/oil packaged unit, $305k–$430k for a biomass chain-grate unit. Pressure, burner class, economiser and auxiliary scope move the figure by 20–40%.

How much gas does a 40 t/h boiler burn per hour?

About 3,069 Nm³/h at full load, assuming 8,500 kcal/Nm³ and 92% thermal efficiency. That is roughly $1,412 per hour at 0.46 USD/Nm³.

What does one efficiency point mean at 40 t/h?

At 8,000 hours a year, one point on a 40 t/h gas unit is roughly 300,000 Nm³ of gas — around $138,000 at 0.46 USD/Nm³. That is why performance guarantees, not list prices, decide these projects.

What is 40 t/h in MW and kcal per hour?

40 t/h is about 28.00 MW, 24,000,000 kcal/h, or roughly 2,560 boiler horsepower.

Sources and further reading

Fuel prices and efficiencies are stated assumptions for comparison, not quotations. Local fuel quality, altitude, feedwater temperature and part-load operation all shift the real number.

Request a quote

Tell us the capacity, fuel and working pressure. Our engineers reply with a technical proposal within one working day.

Or email [email protected] directly.

Partners

Become a Yuanda Boiler agent

We appoint one or two partners per country to quote, deliver and service our boilers locally. Territory protection, factory pricing and commissioning support are part of the agreement.

Apply as an agent
WhatsApp [email protected]
Call WhatsApp Email Get a quote